BSS, Chattogram :
Chattogram Water Supply and Sewerage Authority (CWASA) has taken a Taka 1036 crore water plant project – Bhandal Jhuri Water Supply Project (BJWSP) – aiming to meet the growing water demand of city dwellers.
“The construction work of the project will begin within December this year and the project will be completed by June 2022,” BJWSP project director Mahabubul Alam told BSS.
He said the CWASA has already appointed South Korean consultant firms – Dong Myeong Engineering Consultants, Architecture Company Ltd and Korea & Consortium – and the firms will submit their reports before CWASA within July next.
A tender will be floated for the construction of physical works of the project by the first week of August next, Mahbub said.
He said the acquisition of 50 acres land is completed for constructing two reservoirs on the bank of Karnaphuli River at Justopura village under Boalkhali upazila and power connections have already been given to the project site.
Of the total project cost of Taka 1,036 crore, Korean Exim Bank will finance Taka 754 crore as soft loan while Taka 262 crore will be given by the government exchequer and the rest of the amount of Taka 20 crore will be provided by the CWASA authority.
Mahbub said the water plant project, which includes a 60-kilometre water transmission line, a water treatment plant and two water reservoirs, will generate some 60 million litres of water daily. He said a total of 75 percent water will be supplied to Chattogram south district areas, including Patiya, Anwara, Karnaphuli and Boalkhali upazila from Bhandal Jhuri Water Treatment Plant.
On 5 January, 2016, the Executive Committee of National Economic Council (Ecnec) approved the Bhandal Jhuri Water Supply Project (BJWSP).
CWASA managing director Engr Faizullah told BSS that the production of CWASA now meets only 62 percent water demand of city dwellers.
But, he said, the water demand is on the rise here keeping pace with the growing number of industries and city dwellers.
Chattogram Water Supply and Sewerage Authority (CWASA) has taken a Taka 1036 crore water plant project – Bhandal Jhuri Water Supply Project (BJWSP) – aiming to meet the growing water demand of city dwellers.
“The construction work of the project will begin within December this year and the project will be completed by June 2022,” BJWSP project director Mahabubul Alam told BSS.
He said the CWASA has already appointed South Korean consultant firms – Dong Myeong Engineering Consultants, Architecture Company Ltd and Korea & Consortium – and the firms will submit their reports before CWASA within July next.
A tender will be floated for the construction of physical works of the project by the first week of August next, Mahbub said.
He said the acquisition of 50 acres land is completed for constructing two reservoirs on the bank of Karnaphuli River at Justopura village under Boalkhali upazila and power connections have already been given to the project site.
Of the total project cost of Taka 1,036 crore, Korean Exim Bank will finance Taka 754 crore as soft loan while Taka 262 crore will be given by the government exchequer and the rest of the amount of Taka 20 crore will be provided by the CWASA authority.
Mahbub said the water plant project, which includes a 60-kilometre water transmission line, a water treatment plant and two water reservoirs, will generate some 60 million litres of water daily. He said a total of 75 percent water will be supplied to Chattogram south district areas, including Patiya, Anwara, Karnaphuli and Boalkhali upazila from Bhandal Jhuri Water Treatment Plant.
On 5 January, 2016, the Executive Committee of National Economic Council (Ecnec) approved the Bhandal Jhuri Water Supply Project (BJWSP).
CWASA managing director Engr Faizullah told BSS that the production of CWASA now meets only 62 percent water demand of city dwellers.
But, he said, the water demand is on the rise here keeping pace with the growing number of industries and city dwellers.