BSS, Mymensingh :
Construction of total 46-foot bridges in different areas of the district is nearing completion.
The government is implementing the projects at a cost of Taka over 9.80 crore under the supervision of District Relief and Rehabilitation Office (DRRO).
DRRO sources said bridges are being constructed for developing rural communication network and creating connectivity in the upazila area for the development of rural economy.
Sources said, of the total, three bridges are constructing at a cost of Taka over 67 lakh in Haluaghat upazila, three in Phulpur at a cost of Taka over 67 lakh, two in Gouripur at a cost of Taka 45 lakh, three in Sadar upazila at a cost of Taka over 67 lakh, three in Muktagacha at a cost of Taka over 44 lakh, five in Fulbaria at a cost of Taka over 67 lakh.
Besides, eight bridges in Trisal upazila at a cost of Taka over one crore 61 lakh, four in Iswarganj at a cost of Taka over 65 lakh, three in Nandail at a cost of Taka over 67 lakh, seven in Gaffargaon at a cost of Taka over two crore, three in Bhaluka at a cost of Taka over 67 lakh and two in Dhobaura upazila at a cost of Taka over 44 lakh.
Officer of DRRO M Habibullah told BSS that 90 percent works have already been completed and the rest are likely to be completed by the current month.