Akhaura-Laksam double rly lines okayed

block
UNB, Dhaka :
The Executive Committee of the National Economic Council (Ecnec) at a meeting on Tuesday approved a fresh mega project involving Tk 6,504.55 crore for constructing two duel-gauge double rail lines from Akhaura to Laksam.
Bangladesh Railway will implement the project, titled ‘Construction of Duel Gauge Double Rail Line and Conversion of Existing Rail Line into Dual Gauge between Akhaura and Laksam’, by June 2020.
Briefing reporters after the meeting, Planning Minister AHM Mustafa Kamal said a total of eight development projects were approved at the meeting with Tk 10,625.79 crore.
“Of the total project cost, Tk 2,529.50 crore will come from the national exchequer, Tk 2,618.41 crore from the organisation’s own fund while Tk 5,478.00 crore from project assistance,” he said.
State Minister for Finance and Planning MA Mannan was present at the briefing.
Of the approved eight projects, six are new while two are revised ones.
The total length of the two dual gauge rail lines would be 144 kilometers while another 40-km dual gauge rail line would be constructed for loop and siding lines.
Of the total project cost of Tk 6,504,55 crore for the Dual Gauge Rail Line project, Tk 1,026.66 crore will come from the government exchequer, while the Asian Development Bank (ADB) and the European Investment Bank (EIB) will provide Tk 5,477.88 crore.
The Planning Minister said once the work on Akhaura-Laksam section double dual gauge line is completed, then the entire Dhaka-Chittagong rail line would turn into double dual-gauge ones facilitating transportation of goods and passengers.
Mustafa Kamal said the government is aiming to enhance connectivity with neighbouring countries where Dhaka-Chittagong Rail line would soon turn into a main corridor of the Trans-Asian Railway.
He said, the government is now prioritizing railways and waterways for transportation of goods while on roads and railways for carrying passengers.
The Ecnec meeting gave nod to another project titled ‘Maheshkhali-Anowara Gas Transmission Pipeline’ with Tk 981.90 crore under which 91 kilometer transmission pipeline with a diameter of 30 inch would be set up from Maheshkhali to Anowara to ensure about 500 million cubic feet gas per day to various power plants and fertilizer factories and other industries.
Imported LNG would be supplied through this gas pipeline while work is on to set up an LNG terminal at the deep sea port in Maheshkhali.
The Ecnec meeting approved the ‘Pre-Payment Metering Project for NOCS Division under DPDC’ project with Tk 224.42 crore under which pre-payment metering would be introduced in five areas of Dhaka and Narayanganj.