Tannery owners gets govt. compensation Tk 192.69cr

block
Economic Reporter :
Ministry of Industries compensated the tannery owners who have shifted to the Savar Tannery State with Tk 192.69 crore, reveals the report published by the ministry on the progress of projects, till October 2017.
The ministry had made cumulative expense of Tk 66418.11 lakh on the tannery state project and has achieved 62 per cent progress financially and 80 per cent of the overall development of the tannery state.
The Savar Tannery Estate relocation project began more than ten years ago in an effort to save Dhaka’s river and environment from effluent emitted from more than 200 tanneries at Hazaribagh on the bank of the Buriganga River. The authorities are lagging behind to meet the deadline which forced factories to pollute river Turag due to lack of proper infrastructure over there.
The construction of the Savar tannery state is still under progress. It is a project implemented by Bangladesh Small and Cottage Industries Corporation (BSCIC) under direction of Ministry of Industries.
The authority has completed 97 per cent of civil works of central effluent treatment plant (CETP) and dumping yard. The trial run of four module of CETP is going on after competition of leakage test and permanent electrification cable trench is still under construction over there. The electro-mechanical equipments for CETP have been imported from China and installed for trial run.
According to the progress report, layout plan of 154 industries has been approved among 155 to be transferred from Hazaribagh to Savar. 151 industries have started to construct factories over there.
In the Savar tannery state 96 tannery industries have installed tanning drum and started to process wet blue tannery. Till October 2017, 92 tanneries have started production over there. 145 factories have been applied for electricity connection to the authority and have received demand note. 125 have been deposited fees of demand note and 10 factories have not applied for permanent connection of electricity and 20 factories have not deposited fees for demand note yet.
99 factories have been connected with permanent electricity connection. 36 factories have been connected with gas connection and installed meters and more 6 factories are on the process of getting connected with meter.3 factories are going to be connected with service pipe line, 4 factories have received Material Issue Voucher (MIV) till October 2017. 81 factories have applied for water connection among which 80 have received meter for water connectivity.
Besides, the authority have prepared meter installation pit and gate valve for 205 factories over there to provide connectivity.
block